By BuildGreen · Updated 26 November 2026
BREEAM Very Good requires an overall score of at least 55% and BREEAM Excellent at least 70%. Excellent also adds minimum standards that must be met whatever the total score, mainly in energy, commissioning and operational waste. The extra cost of Excellent depends less on the rating itself than on when the target is set: decided at concept design it is a design choice, decided late it becomes rework.
How BREEAM rating levels work
A BREEAM New Construction assessment awards credits in categories such as management, health and wellbeing, energy, transport, water, materials, waste, land use and ecology, and pollution. Each category has a weighting, and the weighted credits add up to a percentage score. The score sets the rating.
| Rating | Minimum score | How BRE describes it |
|---|---|---|
| Pass | 30% | Standard good practice |
| Good | 45% | Intermediate good practice |
| Very Good | 55% | Advanced good practice |
| Excellent | 70% | Best practice |
| Outstanding | 85% | Innovator |
What separates Very Good from Excellent
The gap is 15 percentage points, and it cannot be closed with low-effort credits alone. Excellent brings additional minimum standards: credits that must be achieved or the rating is capped, however high the total score is.
- Energy: a minimum level of energy performance, shown with an energy model, and sub-metering of major energy uses.
- Commissioning and handover: systems commissioned to a defined standard, with a building user guide.
- Aftercare: seasonal commissioning and support after handover.
- Operational waste: dedicated space and facilities for sorting recyclable waste.
- The exact list depends on the scheme and its version, which is confirmed at pre-assessment.
What Excellent costs compared with Very Good
There is no fixed premium. The cost difference comes from three places: design measures the extra credits need (better envelope and systems, more metering, lower-impact materials), additional studies (for example a life cycle assessment, an ecology report or thermal comfort modelling), and more evidence to manage.
Timing decides how large that is. Several credits must be secured at an early design stage and cannot be recovered later. A project that targets Excellent from concept design chooses those measures while they are cheap; a project that upgrades its target after tender pays for redesign and variations.
How to choose the target
- Check what investors, lenders and anchor tenants require: many set Excellent as the minimum for new offices and logistics.
- Run a pre-assessment at concept design to see the score the current design reaches and the credits available above it.
- Keep a margin of a few percentage points above the threshold, because some credits are lost during construction.
- Compare the cost of the extra credits with the value of the higher rating for financing, leasing and exit.